Applicability
This
procedure applies to claims, controversies or disputes
between the Maricopa County Community College District
and a contractor arising from activities or inactions
on a contract between the two. This includes disagreements
of any kind, such as claims or disputes asserting breach
of contract, mistake, or misrepresentation, contract
modification or rescission, and those regarding interpretation
of the contract and the parties’ responsibilities
under it. It is the policy of the Maricopa County Community
College District to attempt to resolve claims, disputes
or controversies in good faith, engaging the formal
process specified in these procedures only where necessary.
|
| 902.2 |
Authority
The Purchasing Manager
or, for construction and related service contracts,
the Director of Facilities Planning and Development,
or their designees, (“Contract Administrator”)
are authorized to settle and resolve contract claims,
controversies and disputes, subject to the restrictions
and limits of section 902.3 and the procedures of the
Capital Development Advisory Council. Appeals of final
decisions made by the Contract Administrator on a claim,
controversy or dispute may be made to the Director of
Strategic Business Support Services (“Chief Procurement
Officer”) following
the format outlined in section 902.4.
|
| 902.3 |
Restrictions and Limits
Settlement of
a claim is subject, where appropriate, to policies
and practices of the Governing Board requiring its approval
in certain cases.
|
| 902.4 |
Timeliness and Format of the Initial Claim
The Contract Administrator shall initially consider
and resolve claims, controversies and disputes according
to the procedures and within the times specified in the
contract. In any event, any claim, controversy or dispute
must be filed with the Contract Administrator within
180 days after the date that the claim, dispute or controversy
arose.
The claim, controversy or dispute not resolved according
to the contract’s procedures shall be subject
to the procedures specified below. The contractor must
file with the Contract Administrator in writing at
least the following information, and any other information
specified in the contract:
- The name, address, and telephone
number of the contractor and the person representing
the contractor.
- The signature of the person representing
the contractor.
- The contract number or other reference
such as bid or RFP number, which will identify
the contract.
- A statement of the legal and/or factual
grounds on which the
claim is based, including copies of information
relevant to the claim.
- The form of relief requested.
|
| 902.5 |
The Contract Administrator’s Decision
If the claim, controversy or dispute cannot be resolved
by mutual agreement, the Contract Administrator shall
issue a written decision no later than 60 days after
the initial claim, controversy or dispute is filed in
writing. This final decision from the Contract Administrator
shall include:
- A description of the claim;
- Reference to the pertinent contract provisions;
- A statement of the factual areas of agreement or
disagreement;
- A statement of the Contract Administrator’s
decision with supporting rationale;
- A copy of this procedure, which outlines the appeal
process.
A copy of this decision shall be provided to the contractor,
by certified mail – return receipt requested, or
by any other method that provides evidence of receipt. |
| 902.6 |
Issuance of a Timely Decision by the Contract
Administrator
The Contract Administrator may extend the time limit
for a decision for a reasonable time, not to exceed 30
days, but only with the approval of the Chief Procurement
Officer. The Contract Administrator shall notify the
contractor in writing that the time for issuance of a
decision has been extended and the date in which a decision
shall be issued.
If the Contract Administrator fails to issue a decision
within the time allowed, the contractor may proceed as
if the Contract Administrator had issued a decision adverse
to the contractor. |
| 902.7 |
Appeal of the Decision of the
Contract Administrator
The contractor shall have the right
to appeal the decision of the Contract Administrator.
It shall file its appeal with the Chief Procurement
Officer within five days from the date the decision
is received. The appeal shall contain all the information
listed in section 902.4 as well as a statement of
the precise factual or legal error in the decision
of the Contract Administrator from which the appeal
is taken. |
| 902.8 |
Issuance of a Timely Decision by the Chief
Procurement Officer
The Chief Procurement
Officer shall have 30 days in which to render a decision
on the appeal. The time limit for a decision by the
Chief Procurement Officer may be extended for a reasonable
time, not to exceed 30 days, but only upon the approval
of the Vice Chancellor for Business Services in consultation
with legal counsel. If an extension is granted, the
Chief Procurement Officer shall notify the contractor
in writing that the time for issuance of a decision
has been extended and the date in which a decision
shall be issued. |
| 902.9 |
Chief Procurement Officer’s Decision
This final decision from the Chief Procurement Officer
shall include:
- A description of the claim;
- Reference to the pertinent contract provisions;
- A statement of the factual areas of agreement or
disagreement;
- A summary of the procurement officer’s decision;
- A statement of the Chief Procurement Officer’s
decision with supporting rationale;
A copy of this decision shall be provided to the contractor,
by certified mail – return receipt requested, or
by any other method that provides evidence of receipt. |
| 902.10 |
Hearing
The contractor shall make any appeal of the decision
of the Chief Procurement Officer within 5 days of the
receipt of the decision. The contractor shall file the
appeal with the Chief Procurement Officer.
The appeal shall contain all the information listed
in section 902.4 as well as a copy of the decision of
the Chief Procurement Officer and a statement of the
precise factual or legal error in the decision of the
Chief Procurement Officer, from which the appeal is taken.
The Chief Procurement Officer shall notify the Governing
Board or its designee of the appeal. The Governing Board
or its designee shall conduct any hearing on the appeal.
The Governing Board or its designee shall issue a written
decision within 30 days after the appeal has been filed.
The Governing Board or its designee may extend the time
limit for a decision on the appeal for a reasonable time
not to exceed 30 days. The Governing Board or its designee
shall notify the contractor in writing that the time for
the issuance of a decision has been extended and the date
by which a decision will be issued. |
| 902.11 |
Controversies Involving District Claims Against
a Contractor
All claims asserted by the
District against a contractor that are not resolved
by mutual agreement shall promptly be referred by
the Contract Administrator to the Chief Procurement
Officer for a hearing without regard to the procedures
outlined above in sections 902.1 through 902.9. |
Original 05/09/05
Revised 7/28/05
|
|
 |
|
2411
West 14th Street · Tempe, AZ · 85281
|
|
|